客貨共線鐵路信號工程施工技術(shù)規(guī)程(Q/CR 9656-2017 英文版)
定 價:850 元
- 作者:中國鐵路總公司 編
- 出版時間:2018/3/1
- ISBN:9787113241124
- 出 版 社:中國鐵道出版社
- 中圖法分類:U282-65
- 頁碼:111
- 紙張:膠版紙
- 版次:1
- 開本:16開
According to the requirements for establishing the railway construction standard system ofCHINA RAILWAY,this Specification is formulated on the basis of Technical Guide for Constructiono f Mixed Passenger and Freight Railway Signaling System(TZ 206-2007) and Technical Guide for Construction o f ZPW-2000 Track Circuit (Document JGBZ [2011] No. 86) by summarizingthe experience obtained in the construction,operation management and equipment maintenance ofChinese railway signaling projects9 learning from relevant research conclusions, and extensivelysoliciting opinions from construction and operation parties concernecL
This Specification consists of 17 chapters:General Provisions9Terms and Abbreviations,BasicRequirement,Construction Preparation, Optical and Electrical Cables, Fixed Trackside Signal, Switching Equipment, Switch Snow-Melting Equipment, Track Circuit, Balise and Outdoor Line-side Electronic Unit (LEU) ,Indoor Equipment,Hump Signaling Equipment,lnstallation of OtherEquipment,Lightning Protection and Earthing, Single Test, Subsystem Commissioning, SystemInterface Comrrussioning and an appendix.
According to the requirements for establishing the railway construction standard system ofCHINA RAILWAY,this Specification is formulated on the basis of Technical Guide for Constructiono f Mixed Passenger and Freight Railway Signaling System(TZ 206-2007) and Technical Guide for Construction o f ZPW-2000 Track Circuit (Document JGBZ [2011] No. 86) by summarizingthe experience obtained in the construction,operation management and equipment maintenance ofChinese railway signaling projects9 learning from relevant research conclusions, and extensivelysoliciting opinions from construction and operation parties concernecL
This Specification consists of 17 chapters:General Provisions9Terms and Abbreviations,BasicRequirement,Construction Preparation, Optical and Electrical Cables, Fixed Trackside Signal, Switching Equipment, Switch Snow-Melting Equipment, Track Circuit, Balise and Outdoor Line-side Electronic Unit (LEU) ,Indoor Equipment,Hump Signaling Equipment,lnstallation of OtherEquipment,Lightning Protection and Earthing, Single Test, Subsystem Commissioning, SystemInterface Comrrussioning and an appendix.
1 General Provisions
2 Terms and Abbreviations
2.1 Terms
2.2 Abbreviations
3 Basic Requirement
3.1 General Requirement
3.2 Project Owner
3.3 Design lnstitute
3.4 Contractor
3.5 Supervision Firm
3.6 Maintenance Company
4 Construction Preparation
4.1 Construction Investigation and Interface Check
4.2 Design Documents Check
4.3 Selection of Construction Scheme and Allocation of Resources
4.4 Construction Operation Guide
4.5 Construction Technical Clarification
4.6 First Article Inspection and Assessment
5 Optical and Electrical Cables
5.1 General Requirements
5.2 Cable Route Resurvey
5.3 Single Drum Test, Cable Allocation and Transportation
5.4 Cable Laying and Protection
5.5 Through Earthing Wire Laying and Protection
5.6 Cable Splicing
5.7 BoxInstallation, Cable Termination and Wiring
6 Fixed Trackside Signal
6.1 General Requirements
6.2 High Colorlight Signal
6.3 Dwarf Color-light Signal
6.4 Signal Sign Board
6.5 Signal Indicator
7 Switching Equipment
7.1 General Requirement
7.2 Installation Device
7.3 External Locking Device
7.4 Switch Machine
7.5 Switch Closure Detector
7.6 Monitoring Device for Switch Gap
8 Switch Snow-Melting Equipment
8.1 General Requirement
8.2 Installation of Outdoor Equipment
8.3 Installation of Indoor Equipment
9 Track Circuit
9.1 General Requirement
9.2 Compensation Capacitor
9.3 Rail Insulation
9.4 Choke Transformer
9.5 Trackside Equipment of ZPW-2000 Series Track Circuits
9.6 25 Hz Phase Sensitive Track Circuits
9.7 Asymmetrical High Voltage Impulse Track Circuit
9.8 Track Bonds
10 Balise and Outdoor Lineside Electronic Unit (LEU)
10.1 General Requirement
10.2 Balise
10.3 Outdoor Lineside Electronic Unit (LEU)
11 Indoor Equipment
11.1 General Requirement
11.2 Control & Display Equipment
11.3 Power Supply Equipment
11.4 Cabinet and Rack Equipment
11.5 Cable Tray
11.6 Indoor Cabling and Wiring
11.7 Cable Leading-in
12 Hump Signaling Equipment
12.1 General Requirement
12.2 Car Retarder Equipment
13 Installation of Other Equipment
14 Lightning Protection and Earthing
15 Single Test
16 Subsystem Commissioning
17 System lnterface Commissioning
Appendix A Construction Record for Signaling System of
Mixed Passenger and Freight Railway
Normative References
Words used for Different Degrees of Strictness